ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

How can we compress a schedule in project management?

user-image
تم إضافة السؤال من قبل Bassem Al-Ahmad , Financial Director , ADR
تاريخ النشر: 2014/09/02
Salauddin Mohammad
من قبل Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

By applying one of the following three techniques..

1) optimizing activity lead-lag times,2) fast-tracking critical path , and3) crash the critical path.

Syed Waseem Akbar
من قبل Syed Waseem Akbar , Additional Director IT , 5000+ Employee's Company

There should be two ways of doing it as under:-

1. Develop three types of project plans, one is Pessimistic for customer, second is realistic for your management and thrid one is optimistic for your team. The project estimation should be between realistic and optimistic so that any slippage can be managed within it.

 

2. If above is not possible as per your organization requirements then optimizing activity lead-lag time and adjusting resource utilization to100%

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟