ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

In the first six month update on a 1 year, $100,000 project, the analysis shows that the BCWS is $50,000; the BCWP is $40,000 and the ACWP is $30,000.

What can be determined from these figures? 

 

A. The project is behind schedule and over cost.B. The project is ahead of schedule and under cost.C. The project is ahead of schedule and over cost.D. The project is behind schedule and under cost.

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/01/19
Mohamed Galal Hussein Ahmed Mohamed
من قبل Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

 

 

SchedulePerformanceIndexSPI =BCWP/BCWS=40000/50000=0.8<1

 

CostPerformanceIndexCPI= CWP/ACWP=40000/30000=1.33>1

Then the answer is D

 

 

 

 

 

 

 

 

 

 

 

 

 

SchedulePerformanceIndexSPI =BCWP/BCWS=40000/50000=0.8<1

 

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

For me answer A

RAJ DAHIYA
من قبل RAJ DAHIYA , Senior MEP Projects Manager , Trinity Engineering Services L.L.C.

_______________________________________________________________

D. The project is behind schedule and under cost.

_______________________________________________________________

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Yes, the correct answer is

D. The project is behind schedule and under cost.

 

CPI = EV/ AC = 40000/30000  = 1.333  > 1  ===> Below budget.  GOOD

SPI = EV/ PV = 40000/50000  =  .8  < 1   ===> Behind schedule.  NOT GOOD

 

              

Irina Chepel
من قبل Irina Chepel , Personal trainer , Freelancer

It's not exactly my field of the expertise

Muhammad samran
من قبل Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

the answer is D

Divyesh Patel
من قبل Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

I will go with answers given by experts.

hachem hadjira hachem hadjira
من قبل hachem hadjira hachem hadjira , مسؤولة مصلحة بالكلية لحاملي الشهادات ورئيس,التعليم التقييم ،سيرت مكتب شؤون إجتماعية.مكلفة بالمخابر , جامعة العقيد أحمد دراية ولاية أدرار

D. The project is behind schedule and under cost

but i dont now a comtability 

and thinks for your invitation

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟