When a company purchases land with a building on it and immediately tears down the building so that the land can be used ,

for the construction of a plant, the costs incurred to tear down the building should be ?

A. Expensed as incurred.

B. Added to the cost of the plant

C. Added to the cost of the land

D. Amortized over the estimated time period between the tearing down of the building and the completion of the plant.

user-image
تم إضافة السؤال من قبل مستخدم محذوف‎
تاريخ النشر: 2015/10/14
paila harichandrudu paila rajayya
من قبل paila harichandrudu paila rajayya , Asst. Manager (Accounts & Finanace) , Gannon Dunkerley & Co.,Ltd

When a company purchases land with a building on it and immediately tears down the building so that the land can be used.

Farouk Seyadou
من قبل Farouk Seyadou , National operations anager , Saudi Bulk Transport Company Limited

Renovating based on the market need

مقبول محمد جلال علي
من قبل مقبول محمد جلال علي , General Accountant , شركة جودت للمقاولات

..((C.Added to the cost of land ))..