Chilled water pipe installation Highraised apartment building Working pressure : 5.5 bar?

I have installed chilled water pipe in high raised building . There are many pipe drops and ups in building apartment , it is U type shape what is calked bottel trape . My consultant is asking airvent in top of every trap and drain cock at bottom of every trap is Required OR not Kindly advice. 

Building working pressure =5.5 bar

Most horizontal pipe size mm

Whats app : dubai

user-image
تم إضافة السؤال من قبل valay patel , Project Engineer , Trinity Engineering Services
تاريخ النشر: 2015/11/12
Olawale  Olatunde
من قبل Olawale Olatunde , Secondary English Teacher , Titilola Memorial college, osogbo, Osun

NPS-nominal pipe size OD-OUTSIDE DIAMETER

Automatic air vent of the highest and lowest point of piping system. there is no water drain air is drain. Test drain for CHW analysis for chemical treatment in CHW pumps that is circulating and not stagnant. Did you account all pipe losses, this is about 7 to 8 floor system.

Antonio Silva
من قبل Antonio Silva , Maintenance Sub-Director Department , H Seabra - Frio Industrial, SA

Maximum working pressure in any apartment building is3,0 bar (Ashrae).