A finish to finish relationship is defined as which of the following?

 

a. Both activities have to finish at the same time

b. The predecessor has to finish before the successor can finish

c. Both activities are on the critical path

d. The predecessor has a defined lead while the successor has a defined lag

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/16
Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

No.B ..............   a Successor Activity cannot finish until a Predecessor Activity has finished

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option A

Ghada Eweda
من قبل Ghada Eweda , Medical sales hospital representative , Pfizer pharmaceutical Plc.

Agree on expert answers. Thanks

Abdullah Altuwayjiri
من قبل Abdullah Altuwayjiri , PMO Analyst , Qassim University - GDPM

a. Both activities have to finish at the same time

VINOD KUMAR
من قبل VINOD KUMAR , Project Planning Manager , Trags Engineering Qatar

Both activites have to finish at same time irrespective of their start dates.

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

I agree with A option...........

Usman Islam
من قبل Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

A is the correct answer ...........

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B - This is the definition of a finish to finish relationship: I must complete activity ‘a’ before I complete

Activity ‘b’