ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Due to some uncertainty in your project schedule, you have decided to use weighted time estimates for the major deliverables. This type of estimate is also known as?

This type of estimate is also known as?

a. Monte Carlo analysis

b. Beta distribution

c. Parametric estimate

d. Autoregressive moving average

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/16
Ghada Eweda
من قبل Ghada Eweda , Medical sales hospital representative , Pfizer pharmaceutical Plc.

The answer is already given by experts. Thanks

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B – The weighted average uses the beta distribution or PERT technique.  Refer to

PMBOK® Guide, 5th edition, p.171.

 

Correct Answers is 

b. Beta distribution

PERT OR beta distribution technique is used for weighted average.

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

..................  c. Parametric estimate

Sajjad Ali
من قبل Sajjad Ali , Accountant , Livestock and Fisheries Department

This is also called Standard Errors...

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟