ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are the project manager at a large automaker in Japan. Your project involves designing the next generation four wheel drive Sports Utility ?

vehicle for the Asian market. Your project team is attempting to determine the right combination of suspension, tires and chassis that will ensure the stability of SUV at high speeds. Currently, you would like to measure the association between two vehicles: tire size and overall stability. Which of the following diagrams can you use?

A. Control chart

B. Gantt chart

C. Pareto diagram

D. Run chart

E. Scatter chart

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/06/15
Usman Islam
من قبل Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

Option E is correct correlation between two variables

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

E. Scatter chart,

Thanks for invitation

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My oppinion is that the answer is:

E. Scatter chart

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Scatter Chart is the apt answer.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟