You are the project manager at construction company, assigned to build 30-storey apartment building. See below show detail for remaining portion?

 In order to being constructing the frame of the building, the foundation of the building must be built. Which of the following relationship types best describes this dependency between framing and foundation?

A. Start-To-Start 

B. Start-To-Finish

C. Finish-To-Finish

D. Finish-To-Start

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/08/21
Ahmed Salih
من قبل Ahmed Salih , PMO Deputy Director , PM Group

D. Finish-To-Start of course :-)

 

Riad Boughannam
من قبل Riad Boughannam , Civil Engineer , Self Employed

Finish foundations to start framing.

D is correct

Muazzam Achchu Mohamed
من قبل Muazzam Achchu Mohamed , Planning & Control Manager , Sarooj Construction Company LLC

Between Framing & Foundation is Start to Finish.

Start to Finish shall be applicable when it is Between Foundation & Framing 

 

So Correct Answer is C