ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Bar charts are most appropriate for?

 

A. Showing slack time.

B. Comparing actual to planned performance to each activity.

C. All of the other alternatives apply.

D. Showing critical path dependencies.

E. Showing which activities can be rearranged in parallel.

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/01/28
DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. My answer is B. Comparing actual to planned performance to each activity..

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Answer is B - provided Baseline is set while scheduling the activities ; otherwise comparing actual to planned one is not possible.

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. I would like to select B as my answer.

يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Tink you for the invitation

My answer is for  option B

Thanks for the invitations.

 

My answer is Option B) Comparing actual....

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟