ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The critical path is calculated by?

A. determining which tasks have the least amount of total slack.

B. subtracting the end date of task one from the start date of task two.

C. totaling the time for all activities.

D. determining the shortest path through the network.

E. Determining which tasks have the most slack

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/07/22
Binil Paul
من قبل Binil Paul , Senior Planning Engineer , Keo International Consultants - Qatar

option A .........................................

Aneesh Shandilya
من قبل Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option A  

The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. determining which tasks have the least amount of total slack.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟