ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Comparative methods, scoring methods, and economic and cash flow analysis are all part of which of the following?

A. Constrained optimization methods, which are a component of a tool and technique in the Preliminary Scope Statement process B. Benefit measurement methods, which are a component of an input to the Develop Project Charter process C. Benefit measurement methods, which are a component of a tool and technique in the Develop Project Charter process D. Mathematical modes, which are a component of an input to the Preliminary Scope Statement process

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/01/11
Aneesh Shandilya
من قبل Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Thanks for the invite. Option C is the correct answer.

Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the best answer.

ANDRE DOURADO
من قبل ANDRE DOURADO , Design Engineering Manager , Projconsult Engenharia de Projetos Ltda

I believe the B option should be more accurate as answer, to the Benefit measurement methods, cause it is a contributive with some economics aspects of the Develop Project Charter process.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: Benefit measurement methods include comparative methods, scoring models, and cash flow analysis, which are all part of the project selection method tools and techniques in the Develop Project Charter process.

 

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟