Which of the following is NOT a tool or technique of Qualitative Risk Analysis?

A. Probability and impact matrix B. Risk urgency assessment C. Risk categorization D. Expected monetary value analysis

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/06/06
Zameer Bilagi
من قبل Zameer Bilagi , Assistant Vice President , HSBC

Expected monetary value analysis

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: DExplanation: Qualitative Risk Analysis is all about figuring out prioritizing each risk, and figuring out its probability and impact. It's an important part of risk planning. But it's not about coming up with specific numbers! That's what Quantitative Risk Analysis is for - and EMV analysis is part of Quantitative (not Qualitative) analysis, because it's where you assign numeric values to risks.