ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

A project manager reported the following Earned value data: PV: $12,400,000, EV: $14,500,000, AC: $14,500,000 ?

What does this mean? A. The project is under budget and on schedule. B. The project is on budget, but behind schedule. C. The project is on budget and ahead of schedule. D. The project is over budget and on schedule.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/10/03
Abhijit Bera
من قبل Abhijit Bera , Assistant Manager Planning , Tata Projects Ltd

Form the data provided PV = $12,400,000, EV = $14,500,000 & AC = $ 14,500,000

It can be understood that,

1) AC > PV (i.e project is over budget on the specified Data Date)

2) EV > PV (i.e. project is ahead of schedule on the specified Data Date)

so the answer should be "The project is over budget & ahead of schedule" .

As this is not an option, so option (c) can be considered only if AC=BAC on the specified data date.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. The project is on budget and ahead of schedule.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟