ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which of the following best describes the difference between risk audits and risk reviews?

A. Risk reviews are performed on smaller projects, while risk audits are performed on larger projects B. Risk audits should be performed by an outside party, while risk reviews are performed by the project team. C. Risk reviews are also called risk audits D. Risk audits are more proactive responses to project risks, while risk reviews are more reactive responses to risks

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2019/04/17
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Risk audits should be performed by an outside party, while risk reviews are performed by the project team

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟