ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Explain the recognition revenue and expenses using percentage of completion method in long term contract ?

Accountants need a basis to apportion the total contract revenue between the multiple accounting periods. Percentage of completion method provides one of those bases, other being full-contract method. Revenue Recognized = Percentage of Work Completed in the Period Total Contract Value Percentage of work completed is the proportion of work completed in a period to total work for the contract. It is usually estimated using the following formula: Percentage of Work Completed = Expenditures Incurred from Inception to Date Total Estimated Costs for the Contract Expenditures incurred from inception to date represent costs incurred from the start of the project to the date of estimation. Total estimated expenditures for the contract represent the total budgeted cost for the project. It includes costs that have been incurred to date and costs that are expected to be incurred in future periods. . Example Construction Inc. is engaged in constructing a massive bridge in Wonderland. The contract is worth $200 million and the company is expected to complete it in3 years. In Year1 the company has incurred an amount of $50 million on the contract and the engineers estimate that in the next2 years the company is expected to expend $110 million more. Based on the physical progress of the project the engineers also estimate that40% of the work has been carried out. Solution: Percentage of work completed = $50 million ÷ ($50 million + $110 million) =31.25%. Total costs include costs incurred to date and costs expected to be incurred over the remaining period. Based on the percentage of completion calculated using cost date we determine than revenue of $62.5 million has been earned (31.25% multiplied by $200 million total contract value). On the other hand based on the engineer's survey the revenue recognized should be $80 million (40% multiplied by $200 million

user-image
تم إضافة السؤال من قبل mohamed Dahy , CMA Financial Manager , Alissa automotive Group
تاريخ النشر: 2014/03/22
Syed Tanveer Ali
من قبل Syed Tanveer Ali , Account Manager , Myrkott Animation Studio

The Revenue Recognition criteria is dicussed under IAS18 revenue Recognition. But the example and the scenerio you discussed above is from IAS11 Construction Contracts

The questions here how does a company decided what to include as Income & Expenditure for the contract in the statement of Comprehensive income.

 

Stage of Completion is determined by the following three ways under IAS11 

1) Proportion of contract costs incurred for work carried out to DATE

2) Surveys of work carried out 

3)Physical proportion of the contract work completed.

 

As the solution above we must match the cost and revenue for the current period . 

Muhammad Hussain
من قبل Muhammad Hussain , ACCOUNTANT , EPESOL PVT LTD

According to IASB changes your question is dealt as per IFRS15 Revenue from contracts with customers. through input method revenue and expenses will be recognized on the basis of satisfaction of performance obligation.i.e budget consumed out of allocated buget or profit earned out of estimated profit and the like.

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟