Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

When calculating cost variances under a standard costing system we must:

When calculating cost variances under a standard costing system we must: a. Compare standard costs with actual costs at the standard level of activity b. Compare actual costs with those that were budgeted c. Compare actual costs with standard costs at the actual level of output d. Compare actual outputs against budgeted outputs

user-image
Question added by Vinod Jetley , Assistant General Manager , State Bank of India
Date Posted: 2014/10/31
Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

C.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.