The two closing procedures are called:

<p><strong>A. Contract closure and scope verification</strong><strong>B. Close Procurements and Close Project</strong><strong>C. Project closure and product verification</strong><strong>D. Project closure and lessons learned</strong></p>

user-image
Question added by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date Posted: 2015/01/08
Ibrahim Hussein Mayaleh
by Ibrahim Hussein Mayaleh , Sales & Business Consultant and Trainer , Self-employed

I believe (B) Close procurments and Close project

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

  I agree and I have chosen B. Close Procurement and Close Project

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Answer B, just something to know

Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

B. Close Procurements and Close Project

Irina Chepel
by Irina Chepel , Personal trainer , Freelancer

B I think

RAJ DAHIYA
by RAJ DAHIYA , Senior MEP Projects Manager , Trinity Engineering Services L.L.C.

Option B is correct !!

mohammadsadiq kadiri
by mohammadsadiq kadiri , Quality Control Engineer , Nesma telecom and technology

As project is completed we close procurements and the project  itself.

Manjusha Mohan
by Manjusha Mohan , Program Manager , Neo Technology Ltd

Project closure and lessons learnt

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The correct answer is

B. Close Procurements and Close Project