Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are involved in monitoring specific project results to determine whether they comply with relevant quality standards. You are using?

a control chart to illustrate how a process is behaving over time. You've constructed your control chart and determined that all the data points are within the upper and lower control limits of the chart. In addition, seven consecutive data points are observed to be on the one side of the mean. Which of the following is your BEST plan of action?

A. Compare the results from the lat quality management plan

B. No additional action is needed, as the process is within control

C. Adjust the mean based on the observed data points

D. Identify the assignable causes

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/06/14

suitable answer is 

D. Identify the assignable causes

Usman Islam
by Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

option D is best choice.............

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

D. Identify the assignable causes...............

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

yes of coarse , standard quality measures are indication of correct approach to the specfic quality measures it is advisable to be close to them as much as possible , for example if wws scrab rate is defined to be 1% then there is obligation to abide by that standard

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

I thing that the right answer is D

Muhammad Ahmed
by Muhammad Ahmed , Quality Assurance Executive (South Region) , K&Ns Foods Pvt.Ltd.

D. Identify the assignable causes

sardar mardookhy
by sardar mardookhy , PMP certified Project manager , MCCI

D Option,

Thanks for invitation

Sathish Prabhu.V
by Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Yes Option D is the apt answer because 7 concecutive data points from mean means assignable cause should be identified to correct it

kamal purbia
by kamal purbia , IT Project Manager , Automated Systems Company

D. Identify the assignable causes

 

seven consecutive plot point are above or below the mean suggest that process is out of control, therefore identify the assignable causes.

 

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option D

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.