Which of the following tools/ technique of the quality planning process can be used to identify the project variables that will have the?

greatest impact on overall project outcomes and results?

A. Design of experiments

B. Flowcharting

C. Benchmarking

D. Benefit/ cost analysis

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/06/14
Nawar Amane
by Nawar Amane , Consultant , UPVALIS

C- Benchmarking the different variable and try to assess the SWOT of each one

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

A. Design of experiments is right answer

sardar mardookhy
by sardar mardookhy , PMP certified Project manager , MCCI

A. Design of experiments "DOE"

kamal purbia
by kamal purbia , IT Project Manager , Automated Systems Company

Design of experiments is a statistical method for identifying which factors may influence specific variables of a product or process under development or in production.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Design of experiments is the most suitable answer

correct answer is 

A. Design of experiments

Ramzi SAMRI
by Ramzi SAMRI , Industrial engineer , Institut für Betriebliche Bildungsforschung Berlin (IBBF)

I agree with Mr Usman, A is the answer.

Usman Islam
by Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

Option A .. i believe so ...............

Sathish Prabhu.V
by Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Design of Experiments is the apt answer because it ensures the project completion.

Muhammad Ahmed
by Muhammad Ahmed , Quality Assurance Executive (South Region) , K&Ns Foods Pvt.Ltd.

Option A. Design of Experiments