You have just awarded a contract to a outside vendor and developed the corresponding contract management plan. Which process did you just complete?

A. Request sellers

B. Plan contracting

C. Select sellers

D. Plan purchases and acquisitions

E. Contract administration

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/08/14
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-C Select sellers............