Contract file and formal acceptance and closure are outputs of which processes?

A. Information distribution

B. Performance reporting

C. Contract administration

D. Contract closure

E. Manage stakeholders

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/08/14
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-D Contract Closure of project

 