When should the project schedule be developed?

a-As early into the project as possible.A committed schedule should be there before any initiating or planning processes are applied for the project.

 

b-During initiating. The definite project schedule should be developed concurrently with the project contract (if applicable) and the project charter.

 

c-Scheduling should be avoided.  agile approaches with aback log and a weekly to4-weekly meeting cycle are sufficient for modern project management.

 

d-When most planning processes from time,scope,and procurement management have been finished. These will  then be iterated when necessary.

user-image
Question added by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date Posted: 2016/08/27
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-B During initiating. The definite project schedule should be developed concurrently with the project contract (if applicable) and the project charter.

It depends on requirement of contract documents. Usualy milestone time schedule is required during the tender stage. After awarding the contract,  a detailed time schedule (Baseline Program) is submitted within the time limit specified in the contract by the client/management/engineer.

Nadjib RABAHI
by Nadjib RABAHI , Freelancer , My own account

I think the option is :

d- When most planning processes from time, scope, and procurement management have been finished. These will then iterated when necessary.

mohammad khashab
by mohammad khashab , مدير تنفيذي , شركة الكمال للتجارة والمقاولات

First, when prices Make Offer Secondly, when the project work plan

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Option d- is the most apporopriate answer.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

I will prefer option#D ------------------

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

You can estimate a theoratical time table to give the stakeholders an idea, how long it would take to complete a project like this ... perhaps quoting a similar project ... add a few weeks to the time table ... however let them know that you need to adjust this prodiction when all vital information is gathered ...

Usually this will be at the end of the planning stage and lunching the project 

Ahmed Taha
by Ahmed Taha , Digital Director , Home of Performance

in my openion, just a day after the launch. Development is an ongoing progress that never ends. 

Thanks for invitation -

My opinion is the choice - D .

Tge develop schedule process is where the schedule is created and uses the define activities, sequence activities, estimate activity resources, and estimate activity duration’s processes as its inputs hence option D is the Answer.

mohammad al-torbaq
by mohammad al-torbaq , HR. development , L

Sure it will be the answer d-When most planning processes from time,scope,and procurement management have been finished. These will then be iterated when necessary. Because you can't develop the schedule with out the deliverables of other departments plans.

Waleed Hamdy
by Waleed Hamdy , MEP PROJECTS CONTROL HEAD SECTION , AZMEEL CONTRACTING COMPANY

 

d-When most planning processes from time,scope,and procurement management have been finished. These will  then be iterated when necessary.

To Who's select option B -- word "Definite Schedule" is more details then the required/available information in project initiation stage - at that stage only the project expected or required duration as per stakeholder/sponsor requirement 

 