Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is typical for critical chain project management?

A. Management of buffersB. Management of total floats and free floatsC. Management of leads and lagsD. Management of resource over-allocations

user-image
Question added by DR MD ANWAR HOSSAIN , Moderator , bayt.com
Date Posted: 2016/10/12
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Option A

Thanks for invtation

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Of course it is D - Management of resource allocation.

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is option A

Ihab Zaki
by Ihab Zaki , Chief Technology Officer (Cto) , EGID

A. Management of buffers

Project buffer, Feeding buffer and Resource buffer.

Mohammed Asim Nehal
by Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants

The correct answer is :

 A. Management of buffers                                                                                 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.