Going from Level 2 to Level 4 in the work breakdown structure will result in?

 

A. None of the other alternatives apply

B. A greater likelihood that something will fall through the cracks

C. Less estimating accuracy

D. Lower status reporting costs

E. Better control of the project

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/02/03
DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for your invitation. My answer is option A. None of the other alternatives apply.

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. I would like to choose option A as my answer.

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

 

 

Thank you for the invitation

 I agree with  answer A 

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

My first choice is option A & thanks for the invitation .

Mahmoud Mohamed
by Mahmoud Mohamed , senior planning engineer , ACE- Moharram Bakhoum

 

  • E. Better control of the project

Ashraf ELBasyouni
by Ashraf ELBasyouni , PMO DIRECTOR , Hydro for Environmental and Infrastructure Studies

The answer is E which is better control