Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

If the Earned Value is equal to Actual Cost, What does it means?

A. Project is on budget and on schedule

B. There is no schedule variance

C. Schedule Variance Index is1

D. There is no cost variance

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/05/05
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The correct answer is A.

A. Project is on budget and on schedule

ZULFIQAR ALI
by ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

If there is no difference between earned value and actual cost it means that proejct is on budget and schedule.

My answer is A

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is A

A. Project is on budget and on schedule

Keith Gregory Wright
by Keith Gregory Wright , Program Director , DynCorp International

Your project is in trouble. A successful project needs sufficient income to cover direct and indirect costs as well as profit, i would hope that my projects earned value is greater than actual cost, if not i would need to have a strategy to recover losses eg variations etc. Measuring financial position is always problematic as resource costs are realised on different cycles, and as such there are difficult to asses because of the delays. 

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the correct choice

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you option A is good answer.

Krishna Avtar Choudhary
by Krishna Avtar Choudhary , Security Officer , Spicejet Limited

If is an business in a initial stage then its good, and called the no loss no profit stage or break even point. So A

Nagoor Khan
by Nagoor Khan , Transport Manager , worked with different Organizations mentioned in my Resume

The Actual Cost (AC) is a function of the time and it is a measurement of how much money has been spent on a project. It's measured in units of economic value ($). Mathematically, the domain of the Actual Cost (AC) is time and the range is an economic value ($). The Actual Cost (AC) is clearly associated with the Earned Value (EV) because the units of work that are measured by AC, are the same that EV has added as progress. In other words, when a unit of work has been done, EV adds the planned value of cost for that unit of work and AC adds the real cost for that unit of work.

Faheem Memon
by Faheem Memon , Resident Engineer / Discipline Lead , WSP

I have the same situation, but still my SV is negative and SPI is below 0.. How come?

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.