You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test?

production run on your latest project.  Which of the following is the most likely response to this problem?

A. Reduce the technical requirements so that the error is no longer valid.

B. Develop alternative solutions to address the error.

C. Go forward with production, and ignore the error.

D. Go forward with production, but inform the customer of the problem.

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/17

B. Develop alternative solutions to address the error

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with Option B

With greetings and appreciation