A. Develop the project charter
B. Develop the preliminary project scope statement
C. Collect Requirements
D. Develop the project statement of work
Answer: C
Explanation:
< li >After the project manager assigned to a project, Collect Requirements is started.
< li >Develop the project charter is before all of this.