Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In the initiation phase, project manager has been assigned to the project which process that must occur after this?

A. Develop the project charter

B. Develop the preliminary project scope statement

C. Collect Requirements

D. Develop the project statement of work

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/08/26
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

< li >After the project manager assigned to a project, Collect Requirements is started.

< li >Develop the project charter is before all of this.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.