Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers its products through?

 mail-order catalogs.The company is interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, it used a weighted system to make a selection. Which process did this occur in?

A. Request Seller Responses

B. Select Sellers

C. Plan Contracting and Purchases

D. Contract Administration

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/10/13
Mohammed Awad
by Mohammed Awad , Regional Supply Chain & Operations Director , Tamakkon Co.

I would take B as an answer to your question.

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

thank you for the invitation

I agree the option B

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation: Select Sellers involves the receipt of bids and proposals. Weighted systems are one of the tools and techniques of this process used to evaluate vendors based on selection criteria defined by the organization.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.