Your project team has completed the project work. All of the following must be done before the project can be closed EXCEPT:?

A. Make sure the scope of the project was completed B. Get formal acceptance of the deliverables from the customer C. Ensure that the schedule baseline has been updated D. Verify that the product acceptance criteria have been met

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/05/31
Chukwuma Anyanwu
by Chukwuma Anyanwu , Planning Engineer (Lead) , Saipem Contracting Limited

There are too reasons I go for C. First, baseline schedules are never updated. They are a reference point to the progress schedule which are at the beginning of the project are mirrors of the baseline. Secondly, (and assuming the question refers to the baseline as though it where the progress schedule), schedules are not updated at the end but through the project. C

Niranjan Bokil
by Niranjan Bokil , Head-Operations , Signode India Ltd

A,B and D!!

Customer needs to certify that the project work has met all stated and implied needs- scope, deliverables, functional tests, performance tests, documentation!

Morescar Tembo
by Morescar Tembo , Project Officer , Hamad Medical Corporation

A, B and C are essential for the project to be considered complete.  D is the least essential.

Manpreet Singh
by Manpreet Singh , Project Assistant , C-DAC(Center for Development of Advanced Computing)

B and C

We need customer acceptence to verify desired target have been met client expectations and we need to update the company organizational assets beside this documenting the each phase was closed properly after it's completion. 

 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C:

Before you can close your project, there are a few things you need to do. Remember the acceptance criteria in the scope statement? Well, those criteria need to be met. And you need to get formal written acceptance from the customer. And every work item in the WBS needs to be completed. Until the customer accepts the final product, your project isn't done!