Which of the following is considered to be a simulation technique? a. PERT analysis b. GERT analysis c. Monte Carlo analysis d. Critical path method

user-image
Question added by Zakir Muhammed , Contract Administrator , DS Contracting Co.
Date Posted: 2018/06/30
zyad wer
by zyad wer , zyad , oil

 my answer  is pret analysis

Zakir Muhammed
by Zakir Muhammed , Contract Administrator , DS Contracting Co.

Monte Carlo analysis is considered to be simulation technique.