Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

A team member approaches you with a change that could cut your schedule down by a month. What is the first thing you should do?

A. Tell the team member that you've already communicated the deadline for the project, so you can't make any changes now. B. Write up a change request and see if you can get it approved. C. Make the change. It's going to save time and nobody will want the project to take longer than it should. D. Figure out the impact on the scope of the work and the cost before you write up the change request.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/08/15
Greg Cayanan
by Greg Cayanan , SENIOR ASSOCIATE/PARTNER , E. C. YUSON Construction – RMV Construction and Engineering Services Joint Venture

I will review the proposed change/s and compare to the overall approved program and analyze the impact base on time and cost including product quality. There are cases if you make a crash program it will increase the cost tremendously because it will affect your resources, e.g manpower, equipment and materials. Consider if the cost increase is justified that it will not affect the Contractor's cash flow and the owner/client shall not issue an (additional) change order.

Muhammad Naqi Imam Khan
by Muhammad Naqi Imam Khan , Maintenance Manager , Profm-Professional Facility Management ( Alesnad Specialised Limited Co)

I have separate view. I have to study following :

1. Will this change affect quality?

2. Will this change need amendment in the scope of work

3. Will this change increase the cost?

4. And finally will this change generate additional revenue.

Ahmed El Teheiwey
by Ahmed El Teheiwey , Planning Engineer , AIC Steel

D. Figure out the impact on the scope of the work and the cost before you write up the change request.

Joe Abraham
by Joe Abraham , Project Manager , Mohammad Bin Zayed

Will hear completely the approached change then carryout an initial reliability analyzes then share it with the team to see their point of view and besides its risk also will be evaluated then if it is found feasible without affecting the cost and completely abiding with the scope of the project then no issues to proceed with the new proposed change.

Mohammed Aljuboori
by Mohammed Aljuboori , Senior Associate , PMA Consultants

In reality and in general, these types of changes will affect either cost or quality of work or may be both, so you should do a quick VE analysis to list the pros and cons of this change, and see what will be the major benefit to the project to complete it a month earlier, and this is also depends on the type of the project and the entity/person who onws it. 

Andrew Wood
by Andrew Wood , Managing Quantity Surveyor , PROJECTS WITH RED SEA HOUSING SERVICES

D: It is important to communicate the optional change to the key roleplayers to ensure something is not missed when looking at the change from a different perspective. What may be a benifit from one angle may be counterproductive from another.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: DExplanation: Just because the change will help the project's timeline doesn't mean that it will be an overall benefit to the project. It's important to check how the project will impact the other two constraints as part of your change request. Once you know all the facts about the change, the change control board can make an informed decision about how to proceed.

Eko Rasyanto Harimurti
by Eko Rasyanto Harimurti , Manager – Infrastructure Engineering , Bukit Makmur Mandiri Utama

B. Write up a change request and see if you can get it approved.

mohamed khalil mrad
by mohamed khalil mrad , consultant, manager , mkmsolutions

Check all impacts on scope and costs before writing any change request. If the overall project is not negatively impacted, then write the change request.

summy khati
by summy khati , InCharge , M.H. ALSHAYA

D.Figure out the impact on th scope of the work and the cost before you write up the change request.

I should first analyse whether the change is possible and what benefit or harm it can cause based on cost, time and several factors.

if it is benefitting than will request for the approval for the change.

Bousekrane Mohamed reda
by Bousekrane Mohamed reda , Security , Security

Full Name: Bousekrane Mohamed Rida Born on 05/10/1974 Sidi Bel Abbes Nationality Algerian Guard and Security Specialization Obtained a diploma of first degree in the National Gendarmerie after the end of the contract. Thank

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.