Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is typical for Critical chain project management? A. Management of buffers

B. Management of leads and lags C. Management of total floats and free floats D. Management of resource over-allocations

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/10/31
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Management of buffers ----------------

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.