Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

All of the following can be used to estimate the contingency reserves during Activity Duration Estimation EXCEPT: ?

A. Fixed number of work periods B. Quantitative schedule risk analysis C. Percentage of estimated activity duration D. Dependency determination

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/03/28
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Dependency determination -----------------

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.