Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The CPM calculates the earliest start date, earliest finish date, and latest finish date for each activity. ?

Which of the following statements are true regarding the critical path of a project schedule? A. The float/slack time is determined by subtracting the early start date from the early finish date B. The float/slack time is determined by subtracting the early start date from the finish date C. None of the statements are true D. Any project activity with the slack time of zero or greater is considered a critical path

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/05/22

Hello everyone, I want to meet a good girl for a long time, but I just can't do it, it's good that a friend advised the dating site https://www.matchtrace.com/best-dating-sites-for-nerds/. Here I quickly found a pair for myself and now I can feel not lonely. Always live acquaintances with partners who are right for me. I recommend this resource to everyone.

Anthony Hall
by Anthony Hall , IT Expert , Itissalat Al-maghrib

There are so many dating websites but really few of them are worthy. That's why I usually keep the places where I meet people with me. But now I want to speak them out. First of all, grindr review helped me to find someone people for me.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. The float/slack time is determined by subtracting the early start date from the finish date

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.