Which of the following best describes the amount of time one can delay the start of task without delaying the completion of the project?

user-image
Question added by Mohamed El Sayed , Project Manager , Saudi Post
Date Posted: 2014/04/09
Osama Fareez
by Osama Fareez , General Manager , Jordan Vetonit Co. (SAVETO Jordan)

The float of the task itself, also the buffer (as defined in CCPM)  

Mohamed El Sayed
by Mohamed El Sayed , Project Manager , Saudi Post

Total slack

Mahmoud Abdulkader    Darwish
by Mahmoud Abdulkader Darwish , Consultant Bridge Engineer , Brench IDS consulting company

TOTAL FLOAT 

 