Trending Earned Value Management Discussions

Follow

Ask the Community


Ask any professional question and get answers from other specialists.

Stream language
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
5 years ago

A project manager reported the following Earned value data: PV: $12,400,000, EV: $14,500,000, AC: $14,500,000 ?‎

What does this mean? A. The project is under budget and on schedule. B. The project is on budget, but behind schedule. C. The project is on budget and ahead of schedule. ‎ ... See More

Answers:
2
Followers:
Views:
707
Vote Count:
0
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
6 years ago

A project is reporting negative cost variance, what is meant by this? ‎

A . Project is under budget B. Project is over budget C. The project is on budget D. None of the above‎

Answers:
8
Followers:
Views:
15
Vote Count:
4
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
6 years ago

Earned Value Analysis is used to measure performance based on the following parameters?‎

A. Scope and Cost B. Scope and Schedule C. Scope, Cost and Schedule D. Cost and Schedule‎

Answers:
3
Followers:
Views:
76
Vote Count:
3
Answer should contain a minimum of 25 characters.
Tanveer Ahmad Niazi's image
Question added by Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
10 years ago
Answers:
7
Followers:
Views:
216
Vote Count:
9
Answer should contain a minimum of 25 characters.
Tanveer Ahmad Niazi's image
Question added by Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
10 years ago

What would be the best response if the Employer (Client) requests verbally for an additional work? Chose the options below and explain why?‎

Options -1. Accept that -2. Ask for a written request -3. Ask him to let you come back to him after getting feedback from management -4. Ask him to let you come back to h‎ ... See More

Answers:
8
Followers:
Views:
313
Vote Count:
9
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago
Answers:
2
Followers:
Views:
132
Vote Count:
1
Answer should contain a minimum of 25 characters.
Tanveer Ahmad Niazi's image
Question added by Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
10 years ago
Answers:
4
Followers:
Views:
159
Vote Count:
8
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

You are three months into a six month project. Assume the budget burn rate is constant. The budget at...‎

completion (BAC) is $,. AC = $,. The SPI =1.2. What is the CPI of this project? (Round to2 decimal places) a.1. b.1. c.1. d. It cannot be determined from the informa‎ ... See More

Answers:
4
Followers:
Views:
1031
Vote Count:
1
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

You have been keeping careful tabs on a 1 year project via weekly earned value calculations. A key factor... ‎

  is that an early product release will give your organization a decisive competitive advantage in the marketplace. However, at the last stakeholder meeting, one of the ‎ ... See More

Answers:
2
Followers:
Views:
404
Vote Count:
1
Answer should contain a minimum of 25 characters.