Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
5 years ago

Which of the following is the total amount of time that a scheduled activity may be delayed from its early start date without ?‎

delaying the project finish date? A. Critical float B. None of the choices are correct C. Average float D. Total float E. Free float‎

Answers:
2
Followers:
Views:
107
Vote Count:
0
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
5 years ago

You are managing a project with a total budget of $450,000. According to the schedule, your team should have completed 45% of the work by now.?‎

But at the latest status meeting, the team only reported that% of the work has actually been completed. The team has spent $, so far on the project. How would you BEST d‎ ... See More

Answers:
8
Followers:
Views:
48
Vote Count:
1
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
6 years ago
Answers:
6
Followers:
Views:
1918
Vote Count:
4
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
5 years ago

You're managing a project with a schedule performance index (SPI) of 1.07 and a cost performance index (CPI) of 0.94.?‎

How would you BEST describe this project? A. The project is behind schedule and over its budget B. The project is ahead of schedule and within its budget C. The project i‎ ... See More

Answers:
1
Followers:
Views:
343
Vote Count:
0
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
5 years ago

Brandi is a project manager on a software project. About halfway through development, her team found that they had not estimated ?‎

enough time for some of the technical work they needed to do. She requested that the new work be added to the scope statement and that the time to do the work be added to‎ ... See More

Answers:
3
Followers:
Views:
144
Vote Count:
0
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
5 years ago

Post mortem Earned value analysis of a project which is going to be closed showed the following data: SPI: 0.72, CPI: 1.00, What is this telling you? ‎

A. The entire work of the project has been finished behind schedule and on budget. B. The entire work of the project has been finished ahead of schedule and on budget. C.‎ ... See More

Answers:
6
Followers:
Views:
19
Vote Count:
0
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
6 years ago
Answers:
7
Followers:
Views:
18
Vote Count:
3
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

What is the primary purpose of a milestone chart?‎

  A. To show significant events in the project such as completion of key deliverables. B. To show resource constraints. C. To show task dependencies. D. To highlight ‎ ... See More

Answers:
8
Followers:
Views:
106
Vote Count:
3
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

Adjusting Leads and Lags is a technique for?‎

A. Estimate Activity Resources B. Sequence Activities C. Estimate Activity Durations D. Develop Schedule‎

Answers:
9
Followers:
Views:
8
Vote Count:
3
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

Which must be measured regularly to identify variances from the plan?‎

  A. Stakeholder requirements B. Project controls   C. Control Schedule D. Project performance‎