ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Cost performance measurement is BEST done through which of the following?

A. Asking for a percent complete from each team member and reporting that in the monthly progress report

B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance

 

C. Using the50/50 rule and making sure the life cyde cost is less than the project cost

 

D. Focusing on the amount expended last month and what will be expended the following month

user-image
تم إضافة السؤال من قبل Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants
تاريخ النشر: 2015/08/03
Aahyan Mumtaz
من قبل Aahyan Mumtaz , Investment Associate - Growth Equity , Cyan Limited

Option B - Comparing earned value to a measure of input prices (as captured by indexes)

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟