ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Ali's vendor discovered some issues that may escalate the vendor's cost and timelines. What is the best way to proceed forward?

 A.  Sign a new contract 

B.  Follow the Change Control System 

C.  As a new SOW signed by Ali and given to the  vendor    

D. Vendor should, anyway do the additional work and invoice it to the client(Ali's Organization) 

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/06/25
Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

 

thanks for invition ,,,,,,,,,, my choice is option B

Mohammed Nizamul Karim
من قبل Mohammed Nizamul Karim , Technical Officer (Tender Department) , China Railway Construction Co. LTD (CRCC)

My opinion is the right answer is: B

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:

 

D. Vendor should, anyway do the additional work and invoice it to the client(Ali's Organization)

 

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

I prefer to leave answers to Experts. Thanks for Your kind Invitation.

Usman Islam
من قبل Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

Option B is likely........

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

if the issues are included in SOW optionD

if not B.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟