If Contractor fails to fulfill QA/QC requirements on a project, what project management team will take decision against contractor?

A) Project Management Team will request the Client to terminate the Contractor.

B) Project Management Team will instruct the Consultant/Engineer to issue NCR against the Contractor's works to make sure QA/QC requirements.

C) Project Management Team will deduct some percentage(%) from Contractor's Monthly progress Invoice.

D) Project Management Team will warn the contractor and allow him to continue works to complete project on time.

 

 

user-image
تم إضافة السؤال من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
تاريخ النشر: 2016/08/27
Ihab Zaki
من قبل Ihab Zaki , Chief Technology Officer (Cto) , EGID

B Project Management Team will instruct the Consultant/Engineer to issue NCR against the Contractor's works to make sure QA/QC requirements.

Thanks for invitation -

They follow D - C - A Step by Step    !!!

Ammar Fadhil
من قبل Ammar Fadhil , Civil Quality Engineer , Zain - Iraq

make B,D,C and A respectively. 

Pulak Mandal
من قبل Pulak Mandal , Analyst , Accutest research laboratory

they first audit as for sop,and if it not full filled than they can take carrect stape for taht,agenst that .

 

Ashutosh  ranjan
من قبل Ashutosh ranjan , NDT INSPECTOR , Bekem infra project pvt ltd

IT WILL GOOD TO FOLLOW THE PLAN B

Syed Shan Haider
من قبل Syed Shan Haider , Senior Draftsman , Al Marwan General Contracting Company

i am agree with experts...........

 

Project Management Team will deduct some percentage(%) from Contractor's Monthly progress Invoice.

Attia Emad
من قبل Attia Emad , Electrical engineer , Advanced Vision for E/M works

B-Issuing an NCR by the consultant/Engineering (The authorized PM by the sponsor and customer) and circulate the appropriate incharges depts.(Procurements and financial) to deduct a monthly percentage amount of the contractor monetary funding  (funding requirements to complete project objectives)  based upon the contractual and legal obligation on the agreements and the list the contactor in the non-prequalified vendors. By the way there is a sum lump money allocated for the project's formal closure can deduct a certain amount if the vendor failed to meet the customer final requirements and expectations based upon the legal binding relationship .

Marwa Mohammad Basheer
من قبل Marwa Mohammad Basheer , Payroll Unit Head , The Scientific Center

should be handled in a systematic and transparent manner, considering contractual obligations and the overall success of the project.

Shihabeldin Abdelsamad Gasmelsied Hamid  Hamid
من قبل Shihabeldin Abdelsamad Gasmelsied Hamid Hamid , supply section , السفارة الأمريكية بالخرطوم

A) Project Management Team will request the Client to terminate the Contractor.

Pascal Belledent
من قبل Pascal Belledent , Executive Director Operations, Supply Chain & Logistics , Carrefour - Italy

I ask him to redo the work in accordance with the agreements and I charge him a penalty. In the event of a repeat offence, I change supplier.