ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You've identified a risk event on your current project that could save $100,000 in project costs if it occurs. Which of the following is true based?

on this statement? (Choose the best answer.)

A. This risk event should be mitigated to take advantage of the savings.

B. This risk event is an opportunity to the project and should be exploited.

C. This is a risk event that should be accepted, because the rewards outweigh the threat to the

project.

D. This a risk event that should be shared to take full advantage of the potential savings.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/05/26
Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B is the right choice. 

Aneesh Shandilya
من قبل Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option B is the correct answer.

B. This risk event is an opportunity to the project and should be exploited.

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟