You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A schedule change has been?

requested. You know change is concerned with all of the following except which one?

A. Determining that a change occurred

B. Influencing causes of change

C. Verifying change

D. Managing change

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/10/13
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation: Integrated Change Control, Schedule Control, and Cost Control are all concerned with three issues: influencing the things that cause change, determining that change is needed or has happened, and managing the change.

يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

 

Thank you for the detailed and useful answer

 

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟