Where should we place the circuit breaker first? generating station, transformer, or transmission line?

user-image
Question added by Mohmad Rafiq Malla
Date Posted: 2013/09/21
Zia Ullah Baig
by Zia Ullah Baig , Owner , Northern Technologies.

Generator, side, Sub Stations and sure in grid station if you are talikng about large power stations.

Akhtar Masood
by Akhtar Masood , Dispatch Specialist , Abu Dhabi Transmission & Dispatch Company

Generator

Saroj Mahapatra
by Saroj Mahapatra , Senior Power System Planning Consultant , DNV GL

Circuit Breakers are placed in all the avove places.

1.       GCB (Generator Curcuit Breaker) is placed next to generator. This breaker is generally used for gen synchronization

 

2.       Circuit Breaker is placed, before all the transformers / in bus coupler / before all transmission lines.

 

3.       Circuit Breaker is used to protect major equipmets ie., transformer / generator / motor / transmission line

as this question has been asked to me .

i need only ine answer either tranformer , generator etc

Muhammad Adnan Arain
by Muhammad Adnan Arain , Electrical Engineer , Rafhan Maize Products Co.Ltd Incorporate Ingredion

after Generation power  1st installed C.B than give the supply to transformer either we use step up or step down than another C.B installed after that transmit power through transmission line or direct give the supply different feeders.......

mustafa amer
by mustafa amer , مهندس تشغيل , تحكم الكهرباء المصري

Circuit Breaker is used to protect major equipmets ie., transformer / generator / motor / transmission line.

and the most important and expensive  part is generating unit