All of the following statements regarding quality metrics are true EXCEPT:?

 

A. Quality metrics are an input to the Perform Quality Assurance

B. Examples of quality metrics include test coverage, reliability, defect density, failure rate, and availability

C. Quality metrics are an input to the Perform Quality Control

D. None of the choices are correct

E. Quality metrics are an output to the Quality Planning

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/06/17
Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option D

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

D. None of the choices are correct

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:D. None of the choices are correct

عبد الحق شانا
by عبد الحق شانا , freelancer , quality4ever

D. None of the choices are correct.

All of the statements are true except for D. None of the choices are correct. Quality metrics are an input to both Perform Quality Assurance and Perform Quality Control processes. They are used to measure the project's quality and to ensure that it meets the stakeholders' requirements. Examples of quality metrics include test coverage, reliability, defect density, failure rate, and availability. Quality metrics are also an output of the Quality Planning process, where they are identified and defined for use in the project.

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

although the statments are not provided in the question but i guess from the question that you are speaking about non quality metrics as an answer vision is non quaity metric and it is not true quality metric

Correct answer is 

D. None of the choices are correct

Sathish Prabhu.V
by Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Option D is the odd one out.