Create Procurement document is done in -?

A. Conduct Procurements

B. Administer Procurements

C. Plan Procurements

D. Close Procurements

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/07/15
Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

C. Plan Procurements.........................

Graeme McWaters
by Graeme McWaters , Quantity Surveyor , Veolia Westgarth Ltd

C- Plan Procurements, which is the point where the RFQ is Processed.

Khalid shaikh
by Khalid shaikh , Procurement Specialist-(CAPEX, OPEX, MRO spares, Contracts & Shipping management) , Al khalij cement company

In my opinion it should be 'Plan Procurement '

Ahilan R
by Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

 C. Plan Procurements is the answer

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

My choice is C and it should be the right choice because during the planning stage we actually create a procurement document.

S GOKUL
by S GOKUL , Sr.Manager , Vyline Glass Works (Borosil Group)

I firmly believe, the correct response is "C"- Plan Procurements. It is in this phase that the creation of procurement documents vis-à-vis request for proposal (RFP), invitation for bid (IFB), request for quote (RFQ), request for information (RFI), tender notice is processed.

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

I think that the right answer is:

C. Plan Procurements

B. Administering Procurements, needs more documentation procedures such as vendor evaluation, RFQ, PO, etc.,