A. Conduct Procurements
B. Administer Procurements
C. Plan Procurements
D. Close Procurements
C. Plan Procurements.........................
C- Plan Procurements, which is the point where the RFQ is Processed.
C. Plan Procurements is the answer
My choice is C and it should be the right choice because during the planning stage we actually create a procurement document.
I firmly believe, the correct response is "C"- Plan Procurements. It is in this phase that the creation of procurement documents vis-à-vis request for proposal (RFP), invitation for bid (IFB), request for quote (RFQ), request for information (RFI), tender notice is processed.
I think that the right answer is:
C. Plan Procurements
B. Administering Procurements, needs more documentation procedures such as vendor evaluation, RFQ, PO, etc.,