Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Product acceptance criteria should be laid down in which document?

A.  Project scope statement

B.  Work breakdown structure

C.  Resource assignments

D.  Project scope management plan

user-image
Question added by DR MD ANWAR HOSSAIN , Moderator , bayt.com
Date Posted: 2016/10/12

Project scope management plan

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

option A.

Thanks for invitation

Option (A) -------------------------------------

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Looks  A.  Project scope statement  ----------------

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is option A

Ihab Zaki
by Ihab Zaki , Chief Technology Officer (Cto) , EGID

A.  Project scope statement

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Of course it is A - project scope statement 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.