Which may be employed to shorten a schedule without changing the scope of the task?

 

A. Alter to task priorities.

B. Releasing resources earlier from tasks which were scheduled with a late start.

C. Fast tracking or Crashing

D. Fast tracking.

E. Crashing

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/02/11
Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is D

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Than you for invitation. I seem option D. Fast tracking is good answer.

 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Fast tracking    --------------------------

My answer is for option (C) Fast tracking or Crashing

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Option D Fast tracking

 

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Most commonly used ( schedule compression ) practical technique is Crashing .

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Appreciation for your invitation. My answer is Option B.