After which time we can remove shuttering system?

user-image
Question added by Mahmoud alsouqi , Sr Project Engineer , DAR WA EMAAR DEVELOPMENT AND REAL STATE
Date Posted: 2017/05/02
يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

The shutter is removed when the concrete takes sufficient resistance to make it bear its weight 

Hussein Ali
by Hussein Ali , Commercial Manager , Hill-EHAF JV

we should remove the shuttering according to the standards

Md Fazlur Rahman
by Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

Normally to days to provide sufficient time for the concrete to gain above % of the strength.

Engshams Civil
by Engshams Civil , مهندس مدني عام , مكتب هندسي

Thank you for the invitation

 It should be done only after the time that the concrete has gained sufficient strength, at least twice the stress that may be exposed to the concrete when the Formorex is removed. It is also necessary to ensure the stability of the remaining formwork while removing molds

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Though I am not a subject matter expert on this , I have seen my collegues following the method as stated by Mr.Engshams and thanks for the invite.

Jacob P
by Jacob P , IT Project Management Consultant , Eickhoff Wind Asia Pvt Ltd

I am not sure, for colums after48 hours and for side form work for slab and beams for48 hours but for bottom form work after time equal  two times maximum span + two days

Gourab Mitra
by Gourab Mitra , Manager IT Project Program and Delivery Management(Full Time Contract/Consulting Role) , IXTEL(ixtel.com)

Agree with the expert comments

Anish Ali
by Anish Ali , Head Projects , LM Energy & Software Pvt Ltd

I am a Electronics and Telecommunication Engineer and Project Manager in Telecom domain. Request you not to place question pertaining to Civil engineering to me. Regards, ANISH

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with colleagues