Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

During the Develop Schedule process the Project Manager may have to go through several iterations of the schedule before establishing the schedule?

baseline. All of the following are tools and techniques that may be used during this process:

A. GERT, PERT, Leads and Lags

B. Critical Path Method, GERT, Resource Requirements

C. ResourceLevelling Heuristics, Mathematical Analysis, Calendars

D. Duration compression, Resource Leveling Heuristics, PERT

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/07
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Duration compression, Resource Leveling Heuristics, PERT

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.