Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which organization, the project manager has total control of projects?

 A. Projectized organization B. Balanced Matrix organization C. Weak Matrix organization D. Strong Matrix

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/24
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: Projectized organization: The project manager has total control of projects. Personnel are assigned and report to a project manager.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the correct choice.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.